Brand new TDP-2-800 goes to the largest oil-gas fields by the order of GAZPROM NEFT
Section: NewsInnovative TDP-2-800 born inside of I-Pec Engineering OÜ has been successfully tested and put into operation at the sludge pit in Vyngapurovskoye oil and gas field of the Yamal-Nenets Autonomous District.
TDP-2-800 was designed for the recovery of oil from sludge using low-temperature pyrolysis technology by the order of GAZPROM NEFT.
TDP-2-800 testing and commissioning at Vyngapurovskoye oil and gas field
The processing rate is 1500 kg of drilling waste per hour in continuous mode. The recovery outputs are valuable synthetic liquid fuel and dry residue, where the hydrocarbon content is less than 1%. Fully automatic control mode decreases the personnel involvement, the continuous operation raises the equipment performance, which other industrial methods fails to do.